Quick reference

The 60-second RFI model

Draft question → Open RFI → Responses → Official Response → Closed RFI → Distribution

Project TeamDesktop WebVerified July 24, 2026

Draft question → Open RFI → Responses → Official Response → Closed RFI → Distribution

  • The Manager owns coordination.
  • Respondents provide answers. Opening the RFI initially places the ball in their court.
  • Subscribers follow activity but are not automatically responsible for the next response.
  • The Official Response is an accepted response; accepting and closing are separate decisions.
  • Distribution records which question and response attachments were selected and who received the closeout email.